Once the contractor gets over the initial learning curve, 750 to 1000 square feet per day for cast-in-place decks and 1000 to 2000 square feet per day for precast decks is not uncommon. Production rates are dependent upon several factors including but not limited to:
a. Ease of existing deck removal is the existing deck composite or non-composite?
b. Work periods uninterrupted work with detours will be more productive than evening closures.
c. Scope of work replacing interior spans only will take less time than full-width replacement including barriers.
d. Complexity of the bridge geometry more highly skewed structures will require more field labor.
|